February 20, 2003 Meeting Minutes
University of Idaho, Facilities Management, Jack’s Creek
Members Attendance
|
X
|
UI:
Michael Holthaus, Water Systems Coordinator |
X |
WSU:
Joe Kline, Construction Engineer |
|
X
|
UI:
Jay Becker, Assistant Director, Utilities and Engineering |
X
|
WSU:
Rob Corcoran, Assistant Director, Arch., Engr & Const Services |
|
X |
Moscow: Tom Scallorn, Water Dept. Superintendent |
X
|
Pullman: Mark Workman, (Chair), Director Public Works |
|
|
Moscow: Steve Busch, (Vice Chair), City Council Member |
|
Pullman: Art Garro, Maintenance & Operations Superintendent |
|
X |
Moscow: Mark Cook, Dir Public Works |
|
Pullman: Barney Waldrop, City Council Member |
|
X |
Latah
County: Tom Townsend, Citizen and Latah County Representative |
|
Whitman County: Jerry Finch, County Commissioner |
|
X |
Latah County: Tom Stroschein, County Commissioner |
X |
Whitman County: Mark Storey, County Engineer |
VISITORS:
Emily Adams, City of Colfax; Alyssa Douglas, UI grad student; Kent Keller,
Professor, WSU; Farida Leek, WSU grad student; Jim Osiensky, Professor, UI;
Hanxue Qiu, WSU Postdoctoral Research Associate; Andy Rogers, Public Works
Supervisor, Colfax; Kathleen Warnick, interested Citizen; Joan Wu, Professor,
WSU .
1)
Call to
Order and Approval of February 20, 2003 Minutes
Mark
Workman, PBAC Chair, called the meeting to order at 2:35 PM.
The minutes of the
January 16, 2003
meeting were approved by consensus.
2)
While
the Power Point projector was being set up Kirkland gave a quick
update on the Ralph Naylor
LLC pumping application.
The application request has been reduced from 14.35 cfs to 4.08 cfs per day over
the 8 month application period. Since this is less than the 5 cfs request which
automatically requires extra information,
Kirkland
talked to Bob Haynes. He said IDWR is still requiring the extra information for
the Naylor application. The acreage to be irrigated has also been reduced to
199 acres from the 760 previously applied for. If the maximum amount of water
applied for were used it would amount to almost 10 feet in addition to the
approximately 2 feet of normal precipitation for this area. Kirkland said IDWR
will not permit application of more than 3.5 feet per acre according to Bob
Haynes so in reality the peak pumping request might be 4.08 cfs or 1830 gallons
per minute or 2.64 million gallons per day but the actual application of water
to the 199 acres could not exceed 227 million gallons for the 8 month period.
Kirkland said this still appears to be an excessive amount of water to apply in
this area. UI only applies 60 to 70 million gallons of recycled water to the
golf course, arboretum and other green space at the University of Idaho which
totals about 300 acres.
3)
Rob
Corcoran reported on the
status of the new WSU well
drilling.
The contractor, Geotech, has been doing prep work removing several old sheds and
building a settling pond. Corcoran said WSU had decided to drill a 20 inch hole
to 500 feet and then 15 or 18 inches below that. The larger hole is expected to
increase the service life of the well.
4)
Mark Storey reported that eastern Washington/Whitman County
representative Mark Schoesler has offered a bill in the Washington legislature
to change the law to allow cluster development in agriculture areas of
Whitman County such that it works out to 1 residence per 10 acres and up
to1200 gallons of water per day per house from a central well.
5)
Kirkland called attention to a slight revision to the proposed
handout to large pumping applicants in the Palouse Basin area. Workman
asked PBAC members to review it for the next meeting.
6)
Further OK Project Updates and Research Projections by Jim Osiensky and
Kent Keller -
Jim and Kent passed out a progress report on the “Hydrostratigraphic Conditions
in the Palouse Basin,” more commonly designated the OK Project.
Jim Osiensky said much of the work on the OK Project up to this point
has been data collection. Several years of data are ready for serious analysis
to try to build new models that better explain what the data seem to be
showing. Everywhere samples from the Grande Ronde indicate older water which
seems to be saying no new water is getting into the aquifer system. The basin
is hydraulically stable, that is, there is a gradient from the water on the
surface and in the upper aquifer systems to the water in the deeper Grande Ronde
aquifer system. If there were fractures or holes through the strata, surface
and shallow aquifer water should drain naturally into the deep aquifer. Besides
the very effective vertical barriers there also appear to be some horizontal
barriers creating sub-basins in the deep aquifer system. This is a new and
challenging concept. Pumping stress is rapidly transmitted within the
sub-basins but undetected outside the sub-basin. However, on a long-term basis
all the sub-basins are acting as a single basin with water levels falling in a
consistent pattern throughout. To further complicate the sub-basins, some wells
very close together are showing no direct connectivity.
To help figure out a way to put the preliminary conclusions of these data
together in a model that makes sense, Jim proposed the following:
* Improve monitoring across the basin away from the pumping centers by
installing several dedicated, multilevel monitoring wells in select locations.
* Use these monitoring wells plus additional sampling of water geochemistry to
search for recharge and water loss pathways. The long-term water decline seems
to imply that water is being lost from the basin somewhere other than through
the pumping centers.
* Put a team together to work through the data to figure out how to explain the
short-term perturbations in sub-basins with the basin-wide water level declines.
Jim said Jerry Fairley from UI and Joan Wu from WSU were available and
interested in participating.
Jim then talked briefly about the pumping test that was in progress using City
of Moscow well # 9 and University of Idaho well # 4. A quick response was seen
in the Washington DOE observation well but no response was seen in UI well # 3,
which is only 100’s of yards from from the two pumping wells.
This was followed by a discussion of the need for a clear summary of
accomplishments and progress by PBAC and the OK Project which can be handed to
decision makers who are being asked to continue support of PBAC research and
projects. Eventually Kirkland was assigned to work with Keller and Osiensky to
draft a summary sheet that Becker and Workman would review.
7)
Discussion of Possible Request for Federal Funding Help -
Kirkland reported that he had had several discussions with Senator Craig’s
office about the possibility of federal funding help to expedite finding the
most effective solution for stabilizing the deep aquifer water levels and
providing the Palouse Basin with a long-term dependable water supply. A concern
raised by several PBAC members was the amount of match required. After some
discussion of what funds and in-kind participation might be used for matching,
it was agreed that Kirkland should turn in the application limiting direct PBAC
funding participation to no more than the $30,000 presently available in the
budget for matching. To the extent possible, use of state funds and in-kind
matching were encouraged. Kirkland indicated that he would apply for $100,000
for three years. The application is due March 14th. More details
will become available as the request works its way through the appropriate
committees and the hearing process.
8)
Public Involvement -
Townsend said he had been contacted by several citizens
inquiring about the possibility of PBAC holding an evening meeting that would
presumably allow more interested individuals to attend. After some
discussion it was decided to keep the meeting time the same but to go back to
alternating between meeting in Moscow and Pullman. Mark Workman will locate a
meeting room for the next meeting in Pullman.
9)
NEXT MEETING DATE
Since
the next meeting date falls in the week of spring break, several members said
they would not be able to attend. The date was therefore moved back a week to
March 27, 2003.
Thursday, March 27, 2002 at 2:30 pm
Neill Public Library Meeting Room, 210 N. Grand, Pullman
The meeting was adjourned by consensus.
Respectfully Submitted,
Larry
Kirkland
|